Parallel Courses III - Complete Solution Guide
Parallel Courses III is LeetCode problem 2050, a Hard level challenge. This complete guide provides step-by-step explanations, multiple solution approaches, and optimized code in python3, java, cpp, c.
Problem Statement
You are given an integer n , which indicates that there are n courses labeled from 1 to n . You are also given a 2D integer array relations where relations[j] = [prevCourse j , nextCourse j ] denotes that course prevCourse j has to be completed before course nextCourse j (prerequisite relationship). Furthermore, you are given a 0-indexed integer array time where time[i] denotes how many months it takes to complete the (i+1) th course. You must find the minimum number of months needed to complete
Detailed Explanation
The problem asks us to find the minimum number of months required to complete 'n' courses. Each course has a specific duration (given in the 'time' array). Some courses have prerequisites, defined by the 'relations' array, meaning a course can only be started after its prerequisites are completed. We can take multiple courses simultaneously. The goal is to determine the earliest possible completion time for all courses, considering dependencies and course durations.
Solution Approach
The solution uses a combination of topological sort and dynamic programming. First, the input relations are used to build an adjacency list representing the course dependencies. The in-degree of each course is also calculated. Courses with an in-degree of 0 (no prerequisites) are added to a queue. Then, a topological sort is performed using Kahn's algorithm. While processing the queue, we update the completion time of each course's neighbors using dynamic programming. Finally, the maximum completion time among all courses is returned, which represents the minimum time to complete all courses.
Step-by-Step Algorithm
- Step 1: Build the adjacency list (graph) from the 'relations' input and compute the in-degree of each course.
- Step 2: Initialize a 'completion_time' array to store the earliest completion time for each course. Initialize a queue with all courses that have an in-degree of 0 (no prerequisites). Set their completion time to their respective duration from the 'time' array.
- Step 3: Perform topological sort using Kahn's algorithm. While the queue is not empty, dequeue a course 'u'.
- Step 4: For each neighbor 'v' of 'u' (course 'v' depends on 'u'), update the completion time of 'v' as max(current completion time of 'v', completion time of 'u' + time[v-1]).
- Step 5: Decrement the in-degree of 'v'. If the in-degree of 'v' becomes 0, enqueue 'v'.
- Step 6: After the topological sort is complete, find the maximum value in the 'completion_time' array. This is the minimum time required to complete all courses.
Key Insights
- Insight 1: The problem can be modeled as a directed acyclic graph (DAG), where courses are nodes and prerequisites are edges. The topological order of the graph represents a valid sequence in which the courses can be taken.
- Insight 2: Dynamic programming (DP) can be used to compute the earliest completion time for each course. The completion time of a course is the maximum of the completion times of its prerequisites plus its own duration.
- Insight 3: Topological sorting is crucial for processing the courses in a valid order, ensuring that prerequisites are completed before their dependent courses.
Complexity Analysis
Time Complexity: O(n + m)
Space Complexity: O(n + m)
Topics
This problem involves: Array, Dynamic Programming, Graph, Topological Sort.
Companies
Asked at: Acko, Citadel, Snap, Snowflake, Stripe, TikTok, Two Sigma.